Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password

Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.

Study cards for PMP Exam

Quiz yourself by thinking what should be in each of the black spaces below before clicking on it to display the answer.
        Help!  

Question
to design qualityAnswer
6 Processes in Project Time Management   show
🗑
Scheduling Methodology definition   show
🗑
2 common scheduling methodologies.   show
🗑
show schedule management plan  
🗑
Schedule Management plan is a subsidary of or contained in what plan?   show
🗑
3 Inputs to Define Activities Process   show
🗑
show Activity List, Activity Attributes, Milestone List  
🗑
5 Inputs to Sequence Activities Process   show
🗑
2 Outputs from Sequence Activities?   show
🗑
show Activity List, Activity Attributes, Resource Calendars, EEF,OPA  
🗑
3 Outputs of Estimate Activity Resources?   show
🗑
show Activity List, Activity Attributes, Activity Resource Requirements, Resource Calendars, Project Scope Statement, EEF, OPA  
🗑
show Activity Duration Estimates, Project Docuiment Updates  
🗑
show Activity List, Activity Attributes, Project Schedule Network Diagrams, Activity Resource Requirements, Resource calendars, Activity Duration Estimates,Project Scope Statement, EEF, OPA  
🗑
4 Outputs of Develop Schedule   show
🗑
4 Inputs to Control Schedule   show
🗑
5 Outputs of Control Schedule   show
🗑
show -Decomposition -Rolling Wave Planning -Template -Expert Judgement  
🗑
show -Precedence Diagramming method (PDM) -Dependency Dettermination -Applying leads and lags -Schedule network templates  
🗑
show -Expert Judgement -Alternatives Analysis -Published Estimating Data -Bottom up estimating -Project Management Software  
🗑
Tools and Techniques used in Estimate Activity Durations   show
🗑
show -Schedule network Analysis -Critical path method -Critical chain method -Resource leveling -What if scenarion analysis -Applying leads anfd lags -Schedule compression -Scheduling tool  
🗑
Tools & Techniques in Control Schedule   show
🗑
show Precedence Diagramming Method  
🗑
show Activity on Node (AON)  
🗑
show Mandatory - Hard logic Discretionary - Soft logic External - Depends on input from outside the project activities  
🗑
Four relationship Types   show
🗑
show modification of a logical relationship that directs a delay in the successor activity  
🗑
show modification in a logical relationship that allows an acceleration of the successor activity  
🗑
show -One Time -Three Point -Monte Carlo -Analogous Estimating (Top-Down) -Bottom up -Parametric  
🗑
Rolling Wave Planning   show
🗑
3 Schedule Formats?   show
🗑
show Lag  
🗑
show Float or slack  
🗑
Which Scheduling term considers resource limitations and adjusts the schedule to work within those functions   show
🗑
2 Schedule compression techniques   show
🗑
show -Estimate Costs -Determine Budget -Control Costs  
🗑
6 Inputs to Estimate Costs   show
🗑
9 Tools and Techniques of Estimating costs   show
🗑
3 outputs of Estimate Costs   show
🗑
show -Activity Cost Estimates -Basis of estimates -Scioe Baseline =Project Baseline -Resource Calendars -Contacts -OPA  
🗑
5 Tools and Techniques of Determine Budget   show
🗑
3 outputs of determine budget   show
🗑
4 Inputs to Control costs   show
🗑
show -Earned value management -Forecasting -To-Complete Performance Indes (TCPI) -Performance reviews -Variance analysis -Project management software  
🗑
show -Work performance measurements(CV,SV,CPI,SPI for WBS components) -Budget Forecasts(Calculated EAC value or Bottom Up Estimation )-OPA Updates(Variance cause, documented lessons) -Change requests -Project management plan updates -Project document updates  
🗑
What process enables PM to know if they should include funds above estimate to reduce risk of overruns & what are these funds called   show
🗑
What happens to Contingency as project/Activity progresses?   show
🗑
show -Scope Statement -WBS -WBS Dictionary  
🗑
show -Product Description -acceptance criteria -key deliverables -project boundaries -assumptions -constraints about project  
🗑
show Basis of estimate is basically a definition of how the estimates were derived.  
🗑
Define Cost Aggergation   show
🗑
show Contingency reserves & Management reserves  
🗑
Define Management reserves   show
🗑
What is funding limit reconciliation?   show
🗑
show CPB - Cost performance baseline  
🗑
show S-Curve  
🗑
Define EVM   show
🗑
Three deminsions of EVM   show
🗑
Define PV   show
🗑
Total project PV (Two terms)   show
🗑
show Earned Value - value of workperformed expressed in terms of the approved budget assigned to the work activity or WBS component.  
🗑
Define AC   show
🗑
Define SV & Give formula   show
🗑
When does SV always = 0   show
🗑
Define CV & Give formula   show
🗑
Define SPI and give formula   show
🗑
Define CPI and give formula.   show
🗑
show CPI  
🗑
What does the CPI represent in relation to 1   show
🗑
What does PM do when BAC is no longer viable   show
🗑
show Actual cost of work performed plus and ETC (Estimate to Complete) -EAC=ETC(Bottom up) +AC  
🗑
show EAC = AC + BAC - EV (Only use when assuming improved project performance determined by risk analysis)  
🗑
show EAC=BAC/Cumulative CPI -(when assuming consistent performance  
🗑
EAC forecasts for ETC work considering both SPI and CPI- formula and when used   show
🗑
show BAC:(BAC-EV)/(BAC-AC) EAC: (BAC-EV)/(EAC-AC) - Projection of cost performance that must be achieved on remaining work to meet a specific management goal  
🗑
3 types of analysis for performance reviews under EVM   show
🗑
show Magnitude of variation to the cost baseline  
🗑
3 Processes in Quality Management   show
🗑
show Auditing quality requirements and the results from Quality control measurements  
🗑
Quality Vs Grade   show
🗑
show -Scope Baseline -Stakeholder Register -Cost Performance Baseline -Schedule Baseline -Risk Register -EEF -OPA  
🗑
show -Cost benefit analysis -Cost of quality -Control Charts -Benchmarking -Design of experiments -Statistical Sampling -Flowcharting -Proprietary quality management methodologies -Additional Quality planning tools  
🗑
5 outputs of planning quality   show
🗑
4 Inputs to Perform Quality Assurance   show
🗑
3 tools and techniques to perform quality assurance   show
🗑
4 outputs of perform quality assurance   show
🗑
show -Project management Plan -Quality Metrics -Quality Checklist -ork percormance measurements -Approved Change requests -Deliverables -OPA  
🗑
show -Cuase and effect diagram -Control charts - Flowcharting -Histogram -Pareto Chart -Run Chart -Scatter Diagram -Statistical sampling -Inspection -Apprioved Change Request review  
🗑
show QC Measurements -Validated Changes -Validated deliverables -OPA Updates -Change REquests -PMP Updates -Project document updates  
🗑
show -Cost of conformance -cost of nonconformance  
🗑
show entire organization  
🗑
define quality in relation to requirements   show
🗑
Acuracy vs precision   show
🗑
show process of identifying quality requirements and documenting how project will maintain compliance. Throughout project  
🗑
show -Prevention - upfront costs to design quality -Appraisal - Costs associated with evaluating whether the programs or processes meet the requirements  
🗑
3 elements of a HR Plan   show
🗑
show Senior mgt  
🗑
3 types of responsibility chart   show
🗑
show RACI  
🗑
Common format of staffing management plan   show
🗑
show SV=EV-PV  
🗑
Cost Variance(Formula)   show
🗑
Cost Performance Index (Formula)   show
🗑
Schedule Performance Index   show
🗑
EAC Formula   show
🗑
EAC if past variances are expected to be atypical   show
🗑
show EAC=BAC/Cumulative CPI  
🗑
To calculate the budget that will be required to increase the amount of resources to a level that will allow the work to be completed in the remaining time:   show
🗑
show TCPI = (BAC - EV) / (BAC - AC)  
🗑
show TCPI = (BAC - EV) / (EAC - AC)  
🗑
Conduct that results in physical harm or creates intense feelings of fear, humiliation, manipulation, or exploitation in another person is defined as harassment by the PMI code.   show
🗑
PMI Definition of harassment   show
🗑


   

Review the information in the table. When you are ready to quiz yourself you can hide individual columns or the entire table. Then you can click on the empty cells to reveal the answer. Try to recall what will be displayed before clicking the empty cell.
 
To hide a column, click on the column name.
 
To hide the entire table, click on the "Hide All" button.
 
You may also shuffle the rows of the table by clicking on the "Shuffle" button.
 
Or sort by any of the columns using the down arrow next to any column heading.
If you know all the data on any row, you can temporarily remove it by tapping the trash can to the right of the row.

 
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how
Created by: btvennen
Popular Management sets