Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

PMP Chapter 6

QuestionAnswer
A previous project that can be adapted for the current project complete with forms that are pre-populated with organizational specific information are called (BLANK). Template
Planning the immediate portions of the project in detail and the future portions at a higher level is known as (BLANK). Rolling Wave Planning
The work package, which is the smallest component in the WBS, is further broken down into (BLANK) which includes labor managing project time. Schedule Activites
True or False - Since activities are directly derived from the work packages, no activity should fall outside of the project scope. True - Activities should be created directly from the WBS (Scope Baseline).
What are the 3 outputs of the Process 6.2 Define Activities? 1. The Activity List 2. Activity Attributes 3. Milestone List
To ensure the project team has detailed information, each activity is further defined. An identifying number, the preceding and succeeding activities and/or the leads and lags may be included, as well as other info. These are called (BLANK) Activity Attributes
Also known as Mandatory Dependency, this term describes activities that must happen in a particular order. For instance, the dirt must be excavated before the foundation can be built. Hard Logic
Requiring that the painting activity be completed prior to the start of the carpeting installation activity is an example of which PDM activity relationship? Finish to Start
Activities in the (BLANK) have no float and sum to the project duration. Critical Path
True or False - There can be more than one critical path. True
A form of schedule compression that adds resources to an activity on the critical path in an effort to complete rapidly. Crashing
Relying on historical information to predict what current activity durations should be is known as what? Analogous estimating
What are the three estimates that comprise a 3-Point Estimate? Optimistic, Most Likely and Pessimisstic
True or False - 3-Point Averaging should fall closer to the "Most Likely" estimate than PERT. False - PERT weighs the "Most Likely" estimate 4 times more than optimistic or pessimistic.
Positive Time that moves two or more activities further apart and is also known as "waiting" is (BLANK) Lag time
Process 6.7 Schedule Control feeds change requests to what other Project Management Process and Code of Accounts? 4.5 Integrated Change Control
(BLANK) works to modify the project schedule based on the availability of resources rather than activity sequencing. CCM or Critical Chain Method
Crashing adds resources to an activity but it also adds (BLANK). Cost
Created by: lapetti
Popular Computers sets

 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards