Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

PREDICTIVE Formulas

TermDefinition
VARIANCE AT COMPLETION (VAC) DEFINITION DIFFERENCE BETWEEN ORIGINAL BUDGET & NEW FORECASTED BUDGET
TO-COMPLETE PERFORMANCE INDEX (TCPI) DEFINITION PERFORMANCE THAT NEEDS TO BE MET TO BE WITHIN BUDGET FOR THE PROJECT
FREE FLOAT DEFINITION AMOUNT OF TIME YOU CAN DELAY AN ACTIVITY WITHOUT DELAYING THE NEXT ACTIVITY
ESTIMATE AT COMPLETION (EAC) DEFINITION FORECASTING TOTAL PROJECT COST AT END BASED ON THE CURRENT SPENDING RATE OF THE PROJECT
COST VARIANCE (CV) DEFINITION DIFFERENCE BETWEEN WORK DONE & MONEY SPENT
ESTIMATE TO COMPLETION (ETC) DEFINITION FORECASTING AMOUNT NEEDED TO COMPLETE THE CURRENT PROJECT BASED ON CURRENT PERFORMANCE
PLANNED VALUE (PV) DEFINITION AMOUNT OF MONEY WORTH OF WORK THAT SHOULD HAVE BEEN DONE ON THE PROJECT
EARNED VALUE (EV) DEFINITION AMOUNT OF MONEY WORTH OF WORK ACTUALLY DONE ON THE PROJECT
COST PERFORMANCE INDEX (CPI) DEFINITION RATE OF HOW WE ARE SPENDING TO ACTUALLY EARNING ON THE PROJECT
ACTUAL COST (AC) DEFINITION AMOUNT OF MONEY ALREADY SPENT ON THE PROJECT
SCHEDULE VARIANCE (SV) DEFINITION DIFFERENCE BETWEEN AMOUNT OF WORK THAT SHOULD BE DONE VS. WHAT'S ACTUALLY DONE
SCHEDULE PERFORMANCE INDEX (SPI) DEFINITION RATE OF HOW WE ARE MEETING THE PROJECT SCHEDULE
BUDGET AT COMPLETION (BAC) DEFINITION ORIGINAL BUDGET OF THE PROJECT
EAC CALCULATION BAC / CPI
EARLY FINISH CALCULATION ES + D - 1
FLOAT CALCULATION LS - ES OR LF - EF
CV CALCULATION EV - AC
CPI CALCULATION EV / AC
LATE FINISH CALCULATION EF - D +1
FREE FLOAT CALCULATION ES OF NEXT ACTIVITY - EF OF CURRENT ACTIVITY - 1
ETC CALCULATION EAC - AC
SPI CALCULATION EV / PV
EV CALCULATION ACTUAL % / BAC
BUDGET ESTIMATES PERCENTAGES -10 % TO +25%
BETA DISTRIBUTION FORMULA (PERT) OPTIMISTIC EST. + (4*REALISTIC) + PESSIMISTIC EST. / 6
STANDARD DEVIATION FORMULA (PERT) (PESSIMISTIC - OPTIMISTIC) / 6
TCPI CALCULATION (BAC - EV) / (BAC - AC) FOR REMAINING FUNDS
SV CALCULATION EV - PV
BAC CALCULATION TOTAL BUDGETED COST FOR THE PROJECT
TRIANGLE DISTRIBUTION FORMULA (PERT) (OPTIMISTIC + REALISTIC + PESSIMISTIC) / 3
FLOAT IS ALSO KNOWN AS... SLACK OR TOTAL FLOAT
FLOAT DEFINITION AMOUNT OF TIME YOU CAN DELAY AN ACTIVITY WITHOUT DELAYING THE PROJECT
AC CALCULATION SUM OF COST FOR THE GIVEN PERIOD
ROUGH ORDER OF MAGNITUDE ESTIMATE PERCENTAGES -25% TO +75%
DEFINITIVE ESTIMATES PERCENTAGES -5% TO +10%
VAC CALCULATION BAC - EAC
PV CALCULATION PLANNED % COMPLETE * BAC
Created by: justin.olive1
Popular Management sets

 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards