Budgeting, Cost Ctrl
APM PMQ Competence 22 terminology
Term | Definition |
---|---|
Actual cost (AC) | The incurred costs that are charged to the project budget and for which payment has been made, or accrued. |
BAC (Budget at completion) | The sum total of the time-phased budgets. |
Cost breakdown structure (CBS) | The hierarchical breakdown of a project into cost elements. |
Earned value (EV) | A measure of progress that expresses costs committed and work achieved in the same units. |
Earned Value Management | A project control process based on an approach to planning, cost collection and performance measurement. It facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan of performance measurement. |
Organisational breakdown structure (OBS) | A hierarchical way in which the organisation may be divided into management levels and groups, for planning and control purposes. |
Planned cost (PC) | The authorised budget assigned to the scheduled work to be completed. Also referred to as the budgeted cost of work scheduled (BCWS). |
PTPT (Planned total project time) | The baseline duration agreed for the project. |
Work breakdown structure (WBS) | A hierarchical breakdown of the work required to deliver the products of a project. |