Save
Upgrade to remove ads
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

ABH323 (Week 7)

Contract Administration – the End Game

QuestionAnswer
Schedule Management - Progress of the works must be managed to ensure project... progresses and practical completion is reached by the Date for Practical Completion
The superintendent must monitor: - progress and address delays and/or similar concerns at site meetings; - consider when information is required; - consider how to manage interface between design team and - construction team; - consider management of statutory approvals and inspections; - interface with users etc.
Site management: - Storage - Access - Crane access / vertical movement
Site safety - Site inductions - People movement - Vertical and horizontal movement
Setting out Principal typically responsible for survey points
Materials / labour / plant - Deliveries - Site storage - Materials when you/others need them - Double handling - Plant management
Coordination - Between everyone - Between design team and construction team
Insurances - Contractor’s Risk - Care of the Works - Typically from possession of site until 4pm of Date of Practical Completion - Incl. unfixed items if value incl. in payment cert - Things given by Principal to Contractor - Things brought to site by subbies - Temp works, construction plant
Principal’s Risk - Excepted Risks -Negligent act or omission of Princpal, Superintendent, employees/contractors/agents of Principal -Any risk specifically excluded by contract -Use or occupation of Principal of works or part of works -Defects in design other than design by Contractor
Insurances - Main types: - Contract works insurance - Public liability insurance - Workers compensation insurance - Professional indemnity insurance - Existing building insurance (if renovation or other buildings on the land)
Insurances - One or the other party must take out and effect insurance CHECK THE CONTRACT for what is required
Insurances - Contract works insurance: - Covers the works (excludes defective works but covers consequences of it) - Typically must be taken out from date of possession of the site - Typically in place until the Date of Practical Completion (sometimes until 4pm on the Date of Practical Completion) - Principal’s risk from Date of Practical Completion
Insurances - Contract works insurance: - Typically enough insurance cover for all of the following: > Contract sum (e.g. $5M) > Cost of demolition and removal of debris (e.g. $100k) > Cost of consultant’s fees ($100k) > Value of materials supplied by the principal ($50k) > Additional amount or percentage (e.g. 10%)
Insurances - Public Liability Insurance (1) covers Principal, Superintendent, Contractor, all Subcontractors
Insurances - Public Liability Insurance - for: > rights and interests and liabilities to third parties; > loss or damage to property (other than property required to be covered by contract works insurance); and > death of or injury to any person (other than liability under worker compensation insurance)
Insurances - Public Liability Insurance (2) - amount is typically for any one occurrence - $20M is quite common
Insurances - Workers compensation insurance - Required by Workers’ Compensation and Rehabilitation Act 2003 - Covers workers of head contractor and subcontractors
Insurances: Head contractor => Head contractor's workers Subcontractor => Subcontractor's workers
Insurances - Professional Indemnity Insurance: - Covers professional services e.g. design - Covers the entity that provides the prof services
Insurances - Professional Indemnity Insurance: Two types: - ‘claims made’ policy - ‘occurrence based’ policy
‘claims made’ policy - must hold policy when the claim is made - typically required to hold PI insurance for 7 years after end of DLP - typically take out ‘run off’ insurance for balance of 7 years
‘occurrence based’ policy - must hold policy when the event occurred e.g. design was carried out - typically required to hold PI insurance for 7 years after end of DLP - typically don’t need ‘run off’ insurance 
Notice Requirements - Contract clauses will provide time requirements and form requirements for... notices of a claim e.g. variation claim, extension of time claim, delay costs claim, payment claim etc
Notice Requirements - All other claims not covered by a specific clause is typically covered by... a general Claim clause e.g. AS2124 clause 46, AS4000 clause 41
Notice Requirements - Time barred for all claims arising out of or in respect of a breach of... the contract if don’t give claim within time
Notice Requirements - Time runs from when the contractor knew or ought to know when... entitled to make the claim
Notice Requirements - Doesn’t apply to payment claims, variation claims, EOT claims - Incl time to dispute Superintendent’s direction
Practical Completion - Defined by the Contract - It is NOT when work is ‘practically complete’!! - It is when all work has been completed in accordance with the contract AND when all other requirements for PC have been met
Practical Completion - Typically includes: - Provision of certificates (form 15 if design, form 16 for construction, etc) - Provision of Information Documents (as required by Part 6AA QBCC Act for Non-conforming Building Products) - Provision of manufacturer’s warranties - Provision of deed of release - All testing and inspections have been completed - EXCEPT for…
Practical Completion - EXCEPT for: Minor defects or omissions
Practical Completion (1) - Contractor must reach Practical Completion of the Works by the Date for Practical Completion - There is no ‘common’ or ‘industry standard’ definition - Entirely a contractual issue
Practical Completion (2) Typically, contractor claims payment for the full contract price less retention / security permitted to be held after Practical Completion for the correction of defects identified during Defects Liability Period
Defects Liability Period - This is an agreed period of time set by the contract in which the parties have: (1) - agreed how defects in the work identified by the client during the DLP will be communicated to the contractor e.g. weekly report, ad hoc notices, online register, emails - agreed when those defects will be rectified
Defects Liability Period - This is an agreed period of time set by the contract in which the parties have: (2) - agreed consequences if contractor fails to rectify the defective work e.g. client can carry out rectification works itself or engage another contractor to do it then recover costs incurred from payment due to contractor
Defects Liability Period - This is an agreed period of time set by the contract in which the parties have: (3) agreed whether DLP restarts for rectified work
Defects Liability Period - Typically ends 12 mths after PC - If subcontract, typically ends 12 mths after PC of head contract but starts when subcontract reaches PC for subcontract works
Final Completion (1) - Final Completion is the end of the Defects Liability Period - Contract is at an end so Final Payment Claim is made for full contract price including release of all security or retention
Final Completion (2) - Sometimes may be required to give a Deed of Release with Final Claim - Often Final Certificate is taken to be evidence of final entitlements of the parties under the contract IF no notice of dispute is given within 7 days of issue of Final Certificate
Breaches of Contract - If a party does not perform their obligations in accordance with the contract, then it is a breach of the contract - May be a technical breach i.e. it is a breach but no loss has been suffered by the other party - May be a substantial breach i.e. breach of a fundamental term of the contract (e.g. payment, giving access to the site)
Breaches of Contract (1) Party not in breach must decide whether to give a notice of breach and seek remedy of breach (must give reasonable time to remedy – check contract), or take action to enforce specific performance
Breaches of Contract (2) - Must always mitigate loss suffered though - Limitation of liability Act – max time to bring action for breach of contract is 6 years from breach occurring
Contract Termination - If one party is in substantial breach of the contract, non-defaulting party may decide... to terminate the contract BUT must follow process set out in the contract else will be in breach of the contract
Contract Termination - Contract will say what happens on termination e.g.: - Contractor can claim [blah] ……. - Contractor can / cannot submit a claim for payment on date of termination - Unfixed plant and materials - Copyright in plans if design done by or for the contractor
Created by: Asher - S
 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards