How To Implement The Installation Of An Electronics Equipment And/Or System
Question | Answer |
---|---|
What is a "Change to form" | Any Change that affects the weight, balance, or movement of inertia of a component. |
What is an Operational Requirements Document (ORD) | A top-level decision document which establishes the minimum acceptable standards of performance and optimum performance goals for an asset. |
What form must be submitted with a draft TCTO | CG-22 |
Any draft TCTO that proposes an improvement to an asset's operational capability must be accompanied by a _______. | ORD (Operational Requirement Document) |
Which section of the TCTO draft document contains the amplifying information? | Body |
What is the purpose of TCTOs? | REquired for configuration change proposals. Change to form, fit and function. |
How are TCTOs initiated? | By submitting form CG-22 with an attached draft TCTO. |
Step 1 of TCTO process? | Idea |
Step 2 of TCTO process | Submit draft TCTO with CG-22 to be endorsed. |
Step 3 of TCTO process | An improvement in operational capability must be accompanied by an Operational requirements Document (ORD) |
Step 4 of TCTO process | Shall contain as much of this info: Application, purpose, TCTO coordinator, when to be accomplished, by whom to be accomplished, what is required, how work is accomplished, supplemental information, records. |
Step 5 of TCTO process | Product line receives the cg-22 and draft TCTO and forwards to prime unit for initial validation. |
Step 6 of TCTO process | Product line engineering section enters scanned copy of cg-22 and draft TCTO into SFLC central projects database for tracking purposes. There are more steps to TCTO process that are not covered in the course guide. |