Save
Busy. Please wait.
Log in with Clever
or

show password
Forgot Password?

Don't have an account?  Sign up 
Sign up using Clever
or

Username is available taken
show password


Make sure to remember your password. If you forget it there is no way for StudyStack to send you a reset link. You would need to create a new account.
Your email address is only used to allow you to reset your password. See our Privacy Policy and Terms of Service.


Already a StudyStack user? Log In

Reset Password
Enter the associated with your account, and we'll email you a link to reset your password.
focusNode
Didn't know it?
click below
 
Knew it?
click below
Don't Know
Remaining cards (0)
Know
0:00
Embed Code - If you would like this activity on your web page, copy the script below and paste it into your web page.

  Normal Size     Small Size show me how

PMBOK-Acronyms

QuestionAnswer
SPI schedule performance index
RFI request for information
FP-EPA fixed price with economic price adjustment
FFP firm fixed price
CPM critical path methodology
CPAF cost plus award fee
sv schedule variance
RAM responsibility assignment matrix
LOE level of effort
IFB invitation for bid
FMEA failure mode and effect analysis
EV earned value
ETC estimate to complete
EMV expected monetary value
EF early finish date
EAC estimate at completion
cv cost variance
CPI cost performance index<br>A measure of cost efficiency on a project. It is the ratio of earned value (EV) to actual costs (AC). CPI
AC actual cost
ACWP actual cost of work performed
BAC budget at completion
BCWP budgeted cost of work performed
BCWS budgeted cost of work scheduled
CCB change control board
COQ cost of quality
CPF cost plus fee
CPFF cost plus fixed fee
CPlF cost plus incentive fee
ES early start date
EVM earned value management
FF finish-to-finish
FPlF fixed price incentive fee
FS finish to start
LF late finish date
LS late start date
OBS organizational breakdown structure
PDM precedence diagramming method
PMBOK Project Management Body of Knowledge
PMlS project management information system
PMP Project Management Professional
PV planned value
QA quality assurance
QC quality control
RACl "responsible, accountable, consult, and inform"
RBS risk breakdown structure
RFP request for proposal
RFQ request for quotation
SF start-to-finish
SOW statement of work
SS start-to-start
SWOT "strengths, weaknesses, opportunities, and threats"
T time and material
TQM Total Quality Management
WBS work breakdown structure
Created by: esposmp
Popular Standardized Tests sets

 

 



Voices

Use these flashcards to help memorize information. Look at the large card and try to recall what is on the other side. Then click the card to flip it. If you knew the answer, click the green Know box. Otherwise, click the red Don't know box.

When you've placed seven or more cards in the Don't know box, click "retry" to try those cards again.

If you've accidentally put the card in the wrong box, just click on the card to take it out of the box.

You can also use your keyboard to move the cards as follows:

If you are logged in to your account, this website will remember which cards you know and don't know so that they are in the same box the next time you log in.

When you need a break, try one of the other activities listed below the flashcards like Matching, Snowman, or Hungry Bug. Although it may feel like you're playing a game, your brain is still making more connections with the information to help you out.

To see how well you know the information, try the Quiz or Test activity.

Pass complete!
"Know" box contains:
Time elapsed:
Retries:
restart all cards