click below
click below
Normal Size Small Size show me how
3E351B1
CDC II
Question | Answer |
---|---|
(001) What is the first step in locating corner stakes for a building? | Establish a baseline. |
(001) Once the building corners are square, what is the next step taken when preparing a site for concrete? | Erect the batterboards and place the building lines. |
(001) When must you install bracing on batterboards? | If the soil is loose or the stakes are higher than three feet. |
(001) In batterboard construction, how do you hold the building lines securely in place? | Make a saw kerf in the outside edge of each ledger board. |
(001) When excavating around the outside wall planes, how much working space should you allow for form construction? | 2 feet |
(002) When grade stakes are used between wooden footing forms, what action must you take before the concrete sets? | Remove the stakes and fill the holes with concrete. |
(002) How do you form any square or rectangular dimensioned slab using metal forms? | By letting one form end extend past each corner. |
(002) When constructing a footing for a bearing wall, how are the sides held in place with the correct distance maintained between them? | With stakes and spreaders. |
(002) When using 1-inch lumber for slab forms, at what approximate distance should you drive stakes along the board? | 2 feet. |
(002) When using 2-inch lumber for slab forms, at what approximate distance should you drive stakes along the board? | 4 feet. |
(002) How do you reinforce studs that extend over four or five feet when constructing wall forms? | Run double wales horizontally. |
(002) When constructing a new ramp, you must ensure the ramp’s width is not | less than 36 inches. |
(003) When specifications require a No. 5 rebar, what is the actual needed? | ⅝ inch. |
(003) When splicing welded wire fabric, a normal splice made by lapping | one full square plus two inches. |
(003) When constructing footings and other structural members that are against the ground, how much space should you allow between the steel and ground? | 3 inches. |
(003) When reinforcing beams, footings, walls and floors, what should be the minimum clear distance between parallel bars? | 1 inch or 1⅓ times the largest aggregate particle in the concrete. |
(003) When using a pipe sleeve anchor bolt, how do you keep concrete from entering the sleeve? | Pack it with a rag or newspaper. |
(004) When constructing pavements, sidewalks and reinforced concrete buildings, which type of concrete should you use when it must reach its design strength in about 28 days? | Type I. |
(004) When constructing large structures where moderate heat of hydration is needed, what type of cement should you use when it must reach its design strength in about 45 days? | Type II. |
(004) Which type of cement should you use when the concrete must reach its design strength in seven days or less? | Type III. |
(004) Estimate the amount of sand needed to mix one cubic yard of concrete when specifications call for a 1:2:3 mix using 3-inch course aggregates. | 14 cubic feet sand |
(004) Estimate the amount of course aggregate needed to mix one cubic yard of concrete when specifications call for a 1:2:3 mix using 3-inch course aggregates. | 21 cubic feet. aggregate |
(004) When performing a slump test, how should you fill the cone? | In three equal layers, each ⅓ the cone volume |
(005) When hand-mixing concrete, which of the following procedures is correct? | Mix the sand and cement together first, then add the coarse material. |
(005) What is the correct sequence for loading the skip of a concrete mixer? | The coarse aggregate first, the cement second, and the sand third. |
(005) Which of the following concrete joints should you use to separate adjacent structural members to allow differential movement in the vertical plane? | Isolation joint. |
(005) Which of the following concrete joints should you cut into a concrete slab to create a plane of weakness, which force cracking at the joint? | Control joint. |
(006) When pouring concrete in layers, how far should you insert an internal vibrator into the previous layer and why? | Several inches; to assure and good bond. |
(006) You can tell the concrete has been vibrated long enough with an internal vibrator when a | thin mortar line appears on the form’s edge. |
(006) Which of the following actions is used to the strike off the excess concrete to bring the surface to its proper elevation? | Screeding. |
(006) You should begin the edging operation | as the sheen of water begins to leave the surface. |
(006) What action can you take to close hairline cracks (checks) that developed due to a concentration of water and extremely fine aggregates at the surface? | Pound the concrete with a hand float before troweling. |
(007) When the temperature is at or above 50°F, you should cure concrete for at least how many days? | 5 days. |
(007) When the temperature is at or above 70°F, you should cure concrete for at least how many days? | 3 days. |
(007) When using waterproof paper to cure horizontal concrete surfaces, you should lap the adjacent sheets at last how many inches? | 12 inches. |
(007) When using epoxy cement to repair concrete, what is the minimum thickness you can apply it and still retain good strength without cracking? | ⅛ inch. |
(008) What type of mortar should you choose for general use work, specifically for below-grade masonry that contacts the earth, such as foundations? | Type M. |
(008) What is the minimum/maximum time you should mix the mortar when machine mixing? | 3 to 5 minutes. |
(008) When hand-mixing mortar, what method allows the blending process to take place easier and quicker? | Add half the sand, followed by all of the cement and lime, and then the remaining amount of sand. |
(008) As a practical guide, you should discard any mortar not used within | 2½ hours. |
(008) Using Rule 38, estimate approximately how much cement and sand is needed for a 1:4 mix ratio. | 7.6 cubic feet of cement; 30.4 cubic feet of sand. |
(009) When constructing a concrete masonry wall, what action should you take after you locate the corners? | Check the footing or slab for level |
(009) How do you chase the bond for a concrete masonry wall? | Place the first course of blocks without mortar. |
(009) How high should you build the corner leads? | Five or six courses. |
(009) How should you tool mortar joints on a concrete masonry wall? | Tool horizontal joints with a long jointer first, then the vertical joints with an S-shaped jointer. |
(009) Which of the following procedures is used to make a Michigan control joint in a concrete masonry wall? | Lay half- and full-size tongue and groove blocks. |
(009) When installing lintels, what is the minimum amount of bearing that you should provide at each end? | 6 inches. |
(010) What action can you take to ensure that all the face bricks received at the job site are uniform in quality, size and color? | Keep a sample from the first load. |
(010) What do you do to bricks if you must lay them in cold weather? | Keep them dry and warm. |
(010) When laying a brick windowsill, what type of course is used? | Rowlock. |
(010) To protect the tops of walls and other brickwork exposed to the weather, you should install | copings. |
(010) When laying the corner leads on a brick wall, the first lead height is determined by how many | courses are needed and the bond type. |
(010) What size mortar joints should you use when laying brick to produce the strongest and most water-resistant joints? | ¼ and ⅜ inch. |
(011) What action will usually result in efflorescence disappearing with normal weathering? | Stop the source of moisture. |
(011) If you must make repairs to mortar joints after the mortar has already hardened (repointing),you must rake or chisel the old mortar joints at least how deep? | ½ inch. |
(011) Before you insert a replacement brick, you should dampen the new brick and the repair area immediately to | keep the mortar from drying too fast. |
(011) How should you waterproof outside masonry surfaces below ground level where there’s not much water or where drainage is excellent? | Hot asphalt only. |
(012) Which tool is used for further straightening after rodding is completed and to level plaster screeds and finish coats? | Darby. |
(012) Which material can you add to other less workable plaster materials to improve plasticity? | Lime putty. |
(012) Which of the following accessories are used both as finish casings around openings in plaster walls and as screeds around doors and windows? | Casing beads. |
(013) What ingredient does the first number in the plaster mix ratio represent? | Cementitious material. |
(013) What is the usual time needed to mix a batch of plaster to the proper consistency using a mixing machine? | 3 to 4 minutes. |
(013) To repair a structural crack in plaster, you cut out and remove the loose material to form what shape in the crack? | V-shape only. |
(014) When selecting ceramic tiles for interior use, which of the following tiles are suitable? | Nonvitreous and semivitreous. |
(014) When selecting ceramic tile, a class 4 tile suggested use is for | all residential, medium commercial and light institutional floor, and wall areas. |
(015) How do you repair a badly deteriorated plaster wall before you apply ceramic wall tiles? | Remove the old plaster and replaster or cover it with water resistant gypsum wallboard or cement board. |
(015) Before installing ceramic tile, apply a prime coat to the wall when you are using | the adhesive method. |
(015) When installing ceramic tiles around a bathroom sink, place the tiles at least | two courses higher than the sink. |
(015) When laying ceramic tile, how much clearance should you leave between the tile and the tub for contraction and expansion? | ⅛-inch. |
(015) When drilling through ceramic wall tile to mount wall fixtures, how can you keep the drill bit from slipping off the smooth tile surface? | Place two strips of masking tape (form an “X”) on the tile only. |
(016) When installing ceramic floor tile in a bathroom, lay the tile to within what distance of the toilet floor flange? | ½ inch. |
(016) To attain a strong, stiff, squeak-free floor when installing wood underlayment for ceramic tile, install | more fasteners than used with ordinary subfloors. |
(016) When planning for mosaic floor tile in a room that is not square, you | plan any unnecessary cuts for areas that are less noticeable. |
(016) Normally what joint size do you use when laying quarry tile, and how do you maintain the space? | ½ inch; with tile spacers. |
(016) When using a hammer and cold chisel to break the old tile out for replacement, always start from the | center of the tile and work out. |